Basic and Detailed Design of Electric Power Conduit Tunnel of Bukpyeong Thermal Power 345kv Underground Transmission Line

1. Project
Basic and Detailed Design of Electric Power Conduit Tunnel of Bukpyeong Thermal Power 345kv Underground Transmission Line
2. Period
2011.11 ~2015.03
3. Tasks
  • Electric power conduit tunnel: 4 km (opencut 2.8 km, tunnel 1.2 km)
  • Design of structures and temporary facilities for vertical shaft construction
4. Client
KEPCO E&C


SD ENG Co., Ltd.

CEO ㅣ Kim Jaeseok   

Business Registration Number ㅣ 215-87-01960 

TEL ㅣ031-737-2345   FAX ㅣ 031-737-2348  

EMAIL ㅣ sdeng@sdeng.net

ADDRESSㅣ#204, 27, Dunchon-daero 457 beon-gil, Jungwon-gu, Seongnam-si, Gyeonggi-do, Republic of Korea


Copyright (c) SD ENG. All rights reserved

SD ENG Co., Ltd. 

CEO ㅣ Kim Jaeseok    Business Registration Number ㅣ 215-87-01960 

TEL ㅣ031-737-2345   FAX ㅣ 031-737-2348  EMAIL ㅣ sdeng@sdeng.net

ADDRESSㅣ#204, 27, Dunchon-daero 457 beon-gil, Jungwon-gu, Seongnam-si, Gyeonggi-do, Republic of Korea


Copyright (c) SD ENG. All rights reserved