DANGJIN Thermal Power Plant #9&10 - Yard & Flue-Gas Desulfurization Facility Detail Design

1. Project
DANGJIN Thermal Power Plant #9&10 - Yard & Flue-Gas Desulfurization Facility Detail Design
2. Period
2012.03   2015.06
3. Tasks
  • Structural design for wastewater, yard facilities, coal handling facilities, electrical equipment, ash treatment facilities, desulfurization absorption towers, etc.
  • Seismic analysis and structural design of building structures
4. Client
East-West Power Corp/KEPCO E&C


SD ENG Co., Ltd.

CEO ㅣ Kim Jaeseok   

Business Registration Number ㅣ 215-87-01960 

TEL ㅣ031-737-2345   FAX ㅣ 031-737-2348  

EMAIL ㅣ sdeng@sdeng.net

ADDRESSㅣ#204, 27, Dunchon-daero 457 beon-gil, Jungwon-gu, Seongnam-si, Gyeonggi-do, Republic of Korea


Copyright (c) SD ENG. All rights reserved

SD ENG Co., Ltd. 

CEO ㅣ Kim Jaeseok    Business Registration Number ㅣ 215-87-01960 

TEL ㅣ031-722-2347   FAX ㅣ 031-722-2348  EMAIL ㅣ sdeng@sdeng.net

ADDRESSㅣ5F, Humanpalace, 31 Gwangmyeong-ro, Jungwon-gu, Seongnam-si, Gyeonggi-do, Republic of Korea


Copyright (c) SD ENG. All rights reserved